Contingency reserve
Money set aside in a project budget for unknowns, typically 5 to 15 percent of hard costs.
What it means
A contingency reserve is an amount carried in a construction or renovation budget to pay for costs that cannot be identified in advance: unforeseen site conditions, design gaps, code interpretations, and price changes. It is distinct from a replacement reserve, which is an operating-period set-aside for future capital items. A contingency that goes unused is returned to the owner or applied to the loan; one that is exhausted means the owner funds the rest from equity.
Why it matters on the South Shore
Most South Shore commercial renovation involves buildings from the 1950s through the 1980s along Route 18, Route 139, and Route 3A, with original electrical, undocumented additions, and septic systems that may not pass. Site work surprises are routine: ledge in Rockland and Hingham, high groundwater in Marshfield and Plymouth, and contaminated fill in Brockton industrial areas. A 5 percent contingency on these projects is optimism, not planning, and the lender’s inspector will say so.
In practice
An owner-user renovates a 9,000 square foot former auto dealership in Weymouth into a veterinary hospital. Hard costs bid at $1.35 million; the owner carries a 12 percent contingency of $162,000 in the bank budget. During demolition the crew finds a buried hydraulic lift and oil-stained soil, $48,000 to remove and dispose, and the fire department requires a larger water service, $31,000. The contingency covers both, leaving $83,000 for the rest of the job, and the owner never has to write a surprise check.
Straight answers
- How big should a contingency be?
- For new construction with a fixed-price contract, 5 to 7 percent of hard costs is common. For renovation of an older building, 10 to 15 percent, because walls hide problems. Lenders usually require at least 5 percent and control its release. Early in design, before pricing is firm, carry more and shrink it as bids come in.
- Who controls the contingency on a bank-financed project?
- The lender, in most cases. The contingency sits in the loan budget as its own line, and reallocating it to cover an overrun requires the bank's approval, often with the inspector's sign-off. Owners who want freedom keep a separate owner's contingency outside the loan budget, funded from equity, for changes that are their choice rather than a surprise.
Related terms
-
Hard costs vs. soft costs
Hard costs are physical construction; soft costs are the design, permits, fees, and financing around it.
-
Construction loan
A short-term loan that funds a building project in draws as work is completed, repaid by permanent financing or sale.
-
Build-out
The construction work that turns a shell or a prior tenant's space into space ready for a new tenant.
-
Replacement reserve
An annual allowance set aside for the eventual replacement of major building components.
← All 537 terms · Talk to a licensed advisor about your deal →