Entitlements

The government approvals a project needs before it can be built: zoning relief, site plan, wetlands, and permits.

What it means

Entitlements are the discretionary and administrative approvals a property needs before a project can be built or a use can begin: zoning relief, site plan approval, environmental permits, subdivision approval, utility connections, and ultimately building permits. “Entitled land” is land with these approvals in hand, which makes it worth far more than raw land with the same zoning. The entitlement process is where time, cost, and risk concentrate in development.

Why it matters on the South Shore

On the South Shore, entitlements run through three local bodies more often than not: the Planning Board for site plan review, the Zoning Board of Appeals for special permits and variances, and the Conservation Commission for an order of conditions under the Wetlands Protection Act and local bylaws. Each meets once or twice a month, each has its own filing deadlines and abutter notice requirements, and each can continue a hearing. Marshfield, Plymouth, and Duxbury projects almost always touch wetlands buffers; Brockton and Quincy projects more often need parking or dimensional relief.

In practice

A buyer contracts to purchase 3 acres in Hanover for a 24,000 square foot flex building at $1.5 million, contingent on entitlements. The timeline: Conservation Commission order of conditions, four months; Planning Board site plan review, three months, overlapping; ZBA special permit for a reduced buffer, two months. Consultants and legal fees total about $110,000. Eleven months later the buyer closes on an entitled site a lender will finance at 70 percent of cost, and the land is worth roughly $2.1 million with permits.

Straight answers

What entitlements does a typical Massachusetts commercial project need?
Usually some combination of Planning Board site plan review, a special permit or variance from the Zoning Board of Appeals if the use or dimensions need relief, a Conservation Commission order of conditions if wetlands or buffer zones are involved, Board of Health approval for septic, and a curb cut permit from the town or MassDOT. Then the building permit itself.
How long does the entitlement process take?
For a simple as-of-right project with site plan review only, three to five months. Add a special permit and wetlands review and nine to fifteen months is common on the South Shore, longer if a decision is appealed. Massachusetts allows abutters to appeal zoning decisions to court, and an appeal can add a year or more even if you win.

Related terms

Where this term shows up

Terms that point here: Carrying costs · Feasibility study · Development agreement

← All 537 terms · Talk to a licensed advisor about your deal →

Hearing this term in a deal right now?

Call before you sign. A straight read on the clause, the number, or the pitch, usually in one conversation.